Sample Schedule
Here's a sample build schedule (of course, each house is unique).
Construction Tasks
| Week 1 | Floor sheathing, wall framing |
| Week 2 | Wall framing/sheathing, house wrap, truss prep |
| Week 3 | Roof trusses, framing, roof sheathing, tar paper, dried-in |
| Week 4 | Dried-in, back framing, shingling |
| Week 5 | Shingling, back framing, soffit/vinyl trim |
| Week 6 | Back framing, soffit/vinyl trim, siding, porch/stairs |
| Week 7 | Back framing, siding, porch/stairs |
| Week 8 | Siding, deck, framing punchlist |
| Week 9 | Siding, deck, painting trimwork |
| Week 10 | Complete exterior finish, painting, interior trim/doors |
| Week 11 | Painting, interior trim/doors |
| Week 12 | Painting, interior trim/doors, cabinets |
| Week 13 | Painting, caulking, interior trim, closet shelving |
| Week 14 | Painting, caulking, interior trim, closet shelving |
| Week 15 | Finalize painting, caulking, interior trim, cabinets |
| Week 16 | Punchlist, door hardware |
| Week 17 | Punchlist, interior trim, Certificate of Occupancy |
| Week 18 | Punchlist, appliances |
| Week 19 | Walk-thru's & final punchlist |
| Week 20 | Walk-thru's & final punchlist, landscaping |
| Week 21 | Home Dedication and homeowner move-in |